County Road 305 Bridge Replacements
Seven (7) bridges have been identified for replacement along County Road 305. The location of each bridge is shown on the
Bridge Location Map and is identified by Bridge Number. The status of each bridge project is briefly described below. Additional information is included on the
Current Active Projects list.
Bridge No. 734081: Anticipated bridge closure with traffic detour from June 14, 2010 to approx. October 12, 2010. Construction is underway
Bridge No. 734081 Photos
Bridge No. 734082: Project design complete. Construction to begin upon secured funding
Bridge No. 734083: Anticipated bridge closure to begin in the fall of 2010.
Bridge No. 734084: This bridge replacement project has been
completed.
Bridge No. 734085: Anticipated bridge closure with traffic detour from July 15, 2010 to approx October 30, 2010.
Bridge No. 734086: Project design complete. Construction to begin upon secured funding
Bridge No. 734087: Construction activities are in the final stages of completion. The bridge is
OPEN TO THROUGH TRAFFIC as of July 8, 2010
Bridge No. 734087 Construction Photos